Open: Works Orders > Processing > Enter Costs > Operation Times/Costs.
If the operation is not on the list (it is an addition to the estimated operations) or if the works order is a batch order (the works order was not created from an estimate), you will need to enter a Reference and Description manually.
Note: Once created, operations are permanently stored against works orders.
If appropriate, enter the quantity now completed.
If this is not a batch works order, leave the quantity as 0 (zero), or enter 1 as appropriate.
Enter the Labour, Machine, Setup and Subcontract cost times.
Manufacturing has a unique entry system for entering times. You can enter time in any of the following formats:
Entering 65 displays 65h 0m (65 hours zero minutes).
Entering 6{space}5 displays 6h 5m (6 hours 5 minutes).
Entering 6h5m displays 6h 5m (6 hours 5 minutes).
Entering 65m displays 1h 5m (1 hour 5 minutes).
Click in the Costs box from the Enter Operation Times/Costs or Enter Timesheets windows to enter operation costs.
The costs so far recorded against the operation are displayed, broken down over the various cost headings.
Other tasks
Entering timesheets for works orders
Posting non-stock and other expenses
View operation breakdown and details
Reference